One Breach, Two Breach,
Old Breach, New Breach:
An Analysis of Competing Contract Claims in Light of
Bartush-Schnitzius Foods Co. v. Cimco Refrigeration, Inc.
Presented to:
31
st
Annual Construction Law Conference
San Antonio, Texas
Presented by:
Amy K. Wolfshohl
Porter Hedges LLP
Houston, Texas
1
6471760v2
I. Introduction
In disputes involving construction, in many instances the parties are faced with
contractual claims and counterclaims. For example, an owner may assert a claim against a
contractor for defective work while at the same time withholding funds that the contractor seeks
to recover through a contractual claim for payment (among other claims that would likely be
asserted). Another common scenario involves competing delay claims between parties in the
contractual chain. These types of scenarios create “competing breach” claims.
Competing breach claims almost always involve an analysis of who breached first,
whether the claimed breaches were material, and whether a party was required to continue
performing or was entitled to cease its performance. Competing breach claims create complexity
in jury charges and in awarding attorneys’ fees because there may be two valid claims that must
be analyzed. While most decisions focus on claims for material breach, the Texas Supreme
Court recently issued an opinion with respect to a claim involving a non-material breach.
Bartush-Schnitzius Foods Co. v. Cimco Refrigeration, Inc. adds another layer to the analysis of
competing breach claims and highlights the importance of analyzing whether a breach is
immaterial. This paper includes a discussion of the case, how it adds to competing breach
analysis, provides a summary of jury charge issues (including those raised in Bartush) and ends
with a discussion of attorneys’ fees.
II. Discussion of Bartush-Schnitzius Foods Co. v. Cimco Refrigeration, Inc.
A food manufacturer, Bartush-Schnitzius Foods, Co. (“Bartush”), sought to develop a
new line of food which required refrigerated storage that did not exceed 38 degrees.
1
Bartush
contacted a refrigeration contractor, Cimco Refrigeration, Inc. (“Cimco”), to install a new
system.
2
Although Cimco sent Bartush a letter listing three options, the letter did not reference a
particular temperature range for any option.
3
Bartush accepted the most expensive option.
4
When the system was completed, Bartush set the temperature to 35 degrees.
5
This caused
ice to form on the fan motors, which overheated and failed, causing the temperature to increase
at times to 60 degrees.
6
When Bartush discovered the problem, it had already paid Cimco
$306,758 but still owed $113,400.
7
The parties did not agree on how to proceed, and the
manufacturer hired an engineer to investigate the matter.
8
The engineer recommended a warm-
glycol defrost unit,
9
and Bartush hired another contractor to install the unit at a cost of
1
Bartush-Schnitzius Foods Co. v. Cimco Refrigeration, Inc., 518 S.W.3d 432, 434 (Tex. 2017).
2
Id.
3
Id.
4
Id.
5
Id.
6
Id.
7
Id.
8
Id.
9
There is no discussion as to whether the unit constitutes betterment.
2
6471760v2
$168,079.
10
After the warm-glycol defrost unit was installed, the system was able to maintain a
temperature of 35 degrees.
11
Cimco sued Bartush to recover the balance due on the contract.
12
Bartush asserted a
counterclaim for breach of contract, seeking as damages, the cost of the warm-glycol defrost
unit.
13
Cimco asserted in its defense that the equipment it installed was exactly as described in
the accepted purchase order and denied that it had made any guarantee regarding the equipment’s
capacity to maintain a specific temperature.
14
The case was tried to a jury which found: (1) both parties breached the contract,
(2) Cimco breached first, (3) Bartush’s breach was not excused, (4) Bartush was entitled to
$168,079 (the cost of installing the warm-glycol defrost unit), and (5) Cimco was entitled to
$113,400 (the contract balance).
15
The remainder of the case involved interpreting the legal
significance of the jury’s various findings.
a. Trial and Appellate Court Findings
Although the jury found both parties breached the contract and that Bartush’s breach was
not excused, the trial court believed it favored Bartush and rendered judgment in favor of
Bartush for $168,079.
16
The lower court awarded nothing to Cimco, who appealed.
17
In
addition to advocating a different interpretation of the jury verdict, Cimco argued that no
evidence existed that it had breached the contract.
18
The Fort Worth Court of Appeals reversed.
19
The appellate court determined that the
jury’s failure to find Bartush’s breach was excused as necessarily implying a finding that
Cimco’s first breach was nonmaterial.
20
The court of appeals further held that Bartush’s failure
to pay was a material breach as a matter of law, which rendered irrelevant the jury’s finding that
Cimco breached first and precluded Bartush’s recovery.
21
The appellate court remanded to the
trial court for entry of judgment that Bartush take nothing and that Cimco recover $113,400 in
damages.
22
The appellate court did not reach Cimco’s alternative assertion that no evidence
supported the jury’s finding that the contractor had breached the contract.
23
10
Id.
11
Id.
12
Id.
13
Id.
14
Id. at 435.
15
Id.
16
Id.
17
Id.
18
Id. at 438.
19
Cimco Refrigeration, Inc. v. Bartush-Schnitzius Foods Co., 518 S.W.3d 57, 62 (Tex. App.—Fort Worth 2015),
review granted, judgment rev’d, 518 S.W.3d 432 (Tex. 2017).
20
Id. at 61–62.
21
Id. at 62.
22
Id.
23
Bartush-Schnitzius Foods Co., 518 S.W.3d at 438.
3
6471760v2
Both parties appealed to the Texas Supreme Court. Bartush argued that the trial court’s
judgment should be reinstated because the contractor’s first breach was material as a matter of
law and thus excused its subsequent failure to comply with the agreement.
24
Alternatively,
Bartush argued that both damages awards should be given effect, resulting in its net recovery of
$54,679 in compensatory damages.
25
Cimco argued that the court of appeals correctly concluded
that Bartush’s material breach excused Cimco’s nonmaterial breach.
26
b. Supreme Court Decision
In reaching its decision, the Texas Supreme Court distinguished between material and
nonmaterial breach as follows:
“It is a fundamental principle of contract law that when one party
to a contract commits a material breach of that contract, the other
party is discharged or excused from further performance.”
27
By
contrast, when a party commits a nonmaterial breach, the other
party “is not excused from future performance but may sue for
the damages caused by the breach.”
28
Thus, according to the Texas Supreme Court, depending on the severity of the first
breach, a party’s performance may be excused or the non-breaching party may be required to
continue to perform. The court also noted that breach of contract does not require a finding of
materiality. Specifically, “the claim requires a finding of breach, not a finding of material
breach.”
29
In this case, according to the court, materiality was appropriately determined by the jury
unlike in Mustang Pipeline where materiality could be determined as a matter of law.
30
The
court noted that in most cases, materiality presents issues of fact determined by the following
factors outlined in Mustang Pipeline:
(a) the extent to which the injured party will be deprived of the
benefit which he reasonably expected;
(b) the extent to which the injured party can be adequately
compensated for the part of that benefit of which he will be
deprived;
(c) the extent to which the party failing to perform or to offer to
perform will suffer forfeiture;
24
Id. at 435.
25
Id.
26
Id.
27
Id. at 436 (quoting Mustang Pipeline Co. v. Driver Pipeline Co., 134 S.W.3d 195, 196 (Tex. 2004)) (emphasis
added).
28
Id. (quoting Levine v. Steve Scharn Custom Homes, Inc., 448 S.W.3d 637, 654 (Tex. App.—Houston [1st Dist.]
2014, pet. denied)) (emphasis added) (footnote omitted).
29
Id. (citing Mays v. Pierce, 203 S.W.3d 564, 575 (Tex. App.—Houston [14th Dist.] 2006, pet. denied) (“A breach
of contract occurs when a party fails or refuses to do something he has promised to do.”)).
30
Id. at 436–37.
4
6471760v2
(d) the likelihood that the party failing to perform or to offer to
perform will cure his failure, taking account of the
circumstances including any reasonable assurances; and
(e) the extent to which the behavior of the party failing to perform
or to offer to perform comports with standards of good faith
and fair dealing.
31
Here, the jury decided these factors in the context of whether Bartush’s breach was excused
instead of whether Bartush’s or Cimco’s breach was material.
32
Specifically, the jury question
on materiality was as follows:
QUESTION NO. 4
Was BARTUSH’s failure to comply excused?
“Failure to comply” by BARTUSH may be excused if you find that CIMCO previously
failed to comply with a material obligation of the same agreement.
A failure to comply must be material. The circumstances to consider in determining
whether a failure to comply is material include:
(a) The extent to which the injured party will be deprived of the benefit which it
reasonabl[y] expected;
(b) The extent to which the injured party can be adequately compensated for the part of
that benefit of which it will be deprived;
(c) The extent to which the party failing to perform or to offer to perform will suffer
forfeiture;
(d) The likelihood that the party failing to perform or to offer to perform will cure its
failure, taking into account the circumstances including any reasonable assurances;
(e) The extent to which the behavior of the party failing to perform or to offer to perform
comports with standards of good faith and fair dealing.
Answer “Yes” or “No”.
Answer: No
The Supreme Court determined that it could not “overrule the jury’s implied finding” that
Cimco’s breach was not material.
33
Because Cimco’s breach was not material, Bartush was
required to continue its performance (i.e. payment). Bartush’s continued performance, however,
31
Id. (citing Mustang Pipeline, 134 S.W.3d at 199).
32
See id. at 436.
33
Id. at 437.
5
6471760v2
would not discharge its claim for damages against Cimco which had already arisen. In deciding
the case, the court held “[w]hile a party’s nonmaterial breach does not excuse further
performance by the other party, neither does the second breach excuse the first.”
34
In other
words, as stated by the Texas Supreme Court, “a material breach excuses future performance, not
past performance.”
35
Interestingly, there is no discussion regarding whether Bartush’s breach
was material or—if it was immaterial—how that affected the court’s analysis. However, the rule
discussed by the court seems to imply that Bartush’s non-payment was material.
Thus, the Texas Supreme Court found that the Fort Worth Court of Appeals erred in
holding that Bartush’s later, material breach excused Cimco from liability for its breach of its
duty to perform.
36
The Texas Supreme Court agreed with Bartush’s alternative argument in
holding that both parties should be awarded the damages found by the jury, so that Bartush was
entitled to a net award.
37
Except, the Texas Supreme Court remanded to the court of appeals for a
determination of whether there was any evidence that Cimco breached.
38
Accordingly, Bartush’s
claim for a net damage award remains viable unless Cimco prevails on its argument that there
was no evidence of its breach.
III. Analysis
a. Key Finding of Materiality
Key to the Bartush court’s holding is the non-materiality of the original breach. In
particular, the Texas Supreme Court found that Bartush was required to continue to perform and
pay Cimco because Cimco’s breach was nonmaterial. Consequently, in rendering advice to
clients based upon whether to continue to perform after a breach, it is critical to know whether
the breach is material or immaterial. Because only certain breaches are material as a matter of
law, tread lightly on advising clients to discontinue performance.
The following cases discuss: (i) when materiality of a breach can be determined as a
matter of law; (ii) when materiality is a fact question; and (iii) breaches that are not immaterial as
a matter of law.
i. Material Breach Determined as a Matter of Law.
Cases holding that a breach is material as a matter of law are the exception to the rule, but
important to analyzing competing breach claims. The following cases present examples where
material breach could be determined as a matter of law.
In Mustang Pipeline, the Texas Supreme Court determined that a jury need not make an
express finding of materiality when the evidence shows a material breach as a matter of law.
39
34
Id.
35
Id. (emphasis in original).
36
Id. 437–38.
37
See id. at 437.
38
Id. at 438.
39
Mustang Pipeline Co. v. Driver Pipeline Co., 134 S.W.3d 195, 198 (Tex. 2004).
6
6471760v2
Mustang contracted with Driver for the construction of 100 miles of pipeline.
40
During the
bidding phase, Mustang emphasized a completion deadline of April 30, 1997.
41
The parties’
contract contained a “time is of the essence” clause while also contemplating avoidance of
weather-related delays.
42
Claiming extensive weather delays, Driver only completed 15 miles of
pipeline during the first 58-days of a 98-day schedule.
43
With 40 days to complete 85 miles of
pipeline to meet the April 30th deadline, Mustang terminated Driver and hired another contractor
to complete the work. Mustang sued Driver for the cost of completion, lost profits, and
attorneys’ fees.
44
Driver asserted a counterclaim for breach of contract alleging Mustang
wrongfully terminated the contract.
45
After considering factors of material breach laid out in the
Restatement (Second) of Contracts §§ 261–62, the court found that Driver materially breached
the contract as a matter of law, and therefore discharged Mustang from further performance
under the contract.
46
In sum, the Mustang Pipeline court held that Driver breached as a matter of
law because: (i) the contract contained a hard deadline, a time is of the essence clause, and
contemplated avoidance of delays and (ii) an objective inability to cure existed.
Hooker v. Nguyen also addressed material breach as a matter of law.
47
In Hooker, the
owner, Hooker, contracted with Nguyen, the contractor, for the construction of a salon.
48
After
notifying Nguyen of many construction issues, Hooker and Nguyen entered into an agreement by
which Nguyen agreed to remedy the issues and complete the salon by February 4, 2001.
49
Based
on the evidence, the jury found that Nguyen failed to substantially complete his obligations by
February 4.
50
Because Nguyen failed to prove substantial performance, the Fourteenth District
Houston Court of Appeals held that Nguyen materially breached as a matter of law.
51
Therefore,
Hooker was discharged of his obligation to pay the remaining contract price.
52
A similar set of facts are addressed in Casarez v. Alltec Const. Co.
53
The parties’
contract on a home elevation project required substantial completion by a certain date and
included a time is of the essence clause.
54
The contractor could not complete the project without
additional money in excess of the contract price.
55
The homeowners refused to pay the
40
Id. at 196.
41
Id.
42
Id. at 196–97.
43
Id.
44
Id. at 197.
45
Id.
46
Id. at 200.
47
Hooker v. Nguyen, 14-04-00238-CV, 2005 WL 2675018, at *3 (Tex. App.—Houston [14th Dist.] Oct. 20, 2005,
pet. denied).
48
Id. at *1–2.
49
Id. at *2.
50
Id. at *10.
51
Id. This does not apply when the owner is the first to materially breach. 1.9 Little York, Ltd. v. Allice Trading
Inc., 01-11-00390-CV, 2012 WL 897776, at *6 (Tex. App.—Houston [1st Dist.] Mar. 15, 2012, pet. denied) (citing
Tips v. Hartland Developers, Inc., 961 S.W.2d 618, 623 (Tex. App.—San Antonio 1998, no pet.)).
52
Hooker, 2012 WL 897776, at *10.
53
Casarez v. Alltec Const. Co., 14-07-00068-CV, 2007 WL 3287933, at *5 (Tex. App.—Houston [14th Dist.] Nov.
6, 2007, no pet.).
54
Id. at *1, *5.
55
Id. at *5.
7
6471760v2
additional money and the contractor stopped work before the home was substantially complete.
56
Through its failure to achieve substantial completion, the contractor materially breached the
contract as a matter of law and the homeowners were discharged from any remaining contractual
duties.
57
ii. Material Breach Not Determined as a Matter of Law.
In contrast to cases holding that material breach could be determined as a matter of law,
the murky water presented by dueling breach claims is the more common scenario. The
following cases presented the court with material breach claims that could not be determined as a
matter of law.
For example, in MHI Partnership. Ltd. v. DH Real Estate Investment Co., a builder
entered into a contract with a developer to purchase residential lots within a subdivision.
58
An
amendment to the contract required that the developer provide backup information for an
increase or decrease in actual construction and engineering costs three weeks before the closing
date.
59
The developer achieved substantial completion of Phase 1 and demanded closing on lot
sales within the next 10 days.
60
The developer also notified the builder that costs had increased
2%, but such backup information verifying the cost increase was not provided three weeks
before closing.
61
The builder terminated the contract for developer’s failure to provide the
backup information three weeks before closing as provided in the contractual amendment. The
builder asserted such a failure was a material breach of the parties’ contract based on the
“boilerplate” time is of the essence clause in the contract.
62
After a review of the evidence, the
Austin Court of Appeals determined that the parties’ “boilerplate” time is of the essence clause
and circumstances indicated that the parties did not intend the time is of the essence clause to
apply to this particular three week deadline.
63
Therefore, the court could not conclude that the
breach was material as a matter of law and affirmed the trial court’s denial of a directed verdict.
64
In Continental Dredging, Inc. v. De-Kaizered, Inc., a Houston dock owner contracted for
dredging services in front of his dock to a uniform depth of 36-feet.
65
After several ships were
unable to dock, the owner refused to pay the contractor’s outstanding invoice for the material
dredged.
66
At the trial court, the jury determined that the contractor had breached the contract,
but that the breach did not excuse the owner from performance.
67
Thus, the jury impliedly found
that the breach was immaterial.
68
On appeal, the owner argued that the evidence was factually
56
Id.
57
Id. at *6.
58
MHI P’ship, Ltd. v. DH Real Estate Inv. Co., 03-04-00485-CV, 2008 WL 3877717, at *1 (Tex. App.—Austin
Aug. 20, 2008, pet. denied).
59
Id.
60
Id.
61
Id.
62
Id. at *2.
63
Id. at *5–6.
64
Id. at *6.
65
Cont’l Dredging, Inc. v. De-Kaizered, Inc., 120 S.W.3d 380, 386 (Tex. App.—Texarkana 2003, pet. denied).
66
Id. at 387.
67
Id. at 394.
68
Id.
8
6471760v2
and legally sufficient to support a finding that the contractor materially breached as a matter of
law.
69
The Texarkana Court of Appeals disagreed, holding that there was sufficient evidence to
prove that the contractor almost dredged to 36-feet.
70
With sufficient evidence to prove that the
contractor substantially performed, there could be no finding of material breach as a matter of
law.
71
The First District Houston Court of Appeals addressed a material breach claim made by a
Municipal District against a Utility District for its failure to “promptly” bill for water supplied.
72
The contract provided that the Districts would supply water to one another in the event of an
emergency.
73
Thereafter, the providing District was obligated to bill “promptly upon termination
of the Emergency or Temporary Period, whichever is earlier.”
74
From 1999 to 2006, the
Districts’ water supply was carried on account and the offset balance was reported.
75
During this
time, the Municipal District received substantially more water than it supplied to the Utility
District.
76
After determining its need for emergency water had diminished, the Utility District
sent the Municipal District an invoice to settle the account.
77
The Municipal District refused to
pay.
78
One of the Municipal District’s arguments was that the Utility District materially
breached the contract by failing to “promptly” bill, thus excusing the Municipal District’s
obligation to pay.
79
While acknowledging that under a time is of the essence contract a court
may find a material breach as a matter of law, the Houston Court of Appeals concluded that was
not the intent of the parties in this case.
80
The First District Houston Court of Appeals in GCC Constructors, Inc. v. American
Horizon Concrete, Inc., held that evidence presented at the trial court was insufficient to find that
the subcontractor’s abandonment of a construction project after late payment was a material
breach as a matter of law.
81
GCC, a first-tier subcontractor, contracted with American Horizon,
a second-tier subcontractor, for concrete work, including both materials and manpower.
82
The
subcontract did not contain a completion date or impose a work schedule.
83
While the
subcontract did contain a time is of the essence clause, the same provision allowed for GCC to
amend American Horizon’s work schedule.
84
It was undisputed that American Horizon
abandoned the project after only partial performance.
85
American Horizon alleges that it
69
Id. at 393–94.
70
Id. at 395.
71
Id.
72
Harris Cty. Util. Dist. No. 16 v. Harris Cty. Mun. Dist. No. 36, 01-10-00042-CV, 2011 WL 3359698, at *9 (Tex.
App.—Houston [1st Dist.] Aug. 4, 2011, no pet.).
73
Id. at *1.
74
Id.
75
Id. at *2.
76
Id.
77
Id.
78
Id.
79
Id. at *9.
80
Id. (citing Mustang Pipeline Co. v. Driver Pipeline Co., 134 S.W.3d 195, 196 (Tex. 2004)).
81
GCC Constructors, Inc. v. Am. Horizon Concrete, Inc., 01-04-00817-CV, 2007 WL 926652, at *5 (Tex. App.—
Houston [1st Dist.] Mar. 29, 2007, no pet.).
82
Id. at *1.
83
Id.
84
Id.
85
Id.
9
6471760v2
abandoned the project because of GCC’s failure to pay, delays not entirely caused by American
Horizon, and requests for expedited work without pay.
86
The trial court found that GCC
breached the contract awarding American Horizon $40,000 in damages.
87
On appeal, GCC
claimed that under Mustang Pipeline’s analysis, the facts indicate that American Horizon
breached the subcontract, and GCC was also excused from its financial obligation to pay.
88
While the court recognized that the subcontract contained a time is of the essence clause, GCC-
American Horizon’s circumstances differed from those of Mustang Pipeline.
89
Unlike in
Mustang Pipeline, the need for timely performance was only one of several issues GCC and
American Horizon disputed.
90
Furthermore, the majority of delays on the project did not stem
from American Horizon.
91
In sum, because the trial court was required to resolve the parties’
factually disputed allegations concerning timely performance and causal delays, the appellate
court overruled GCC’s argument that American Horizon materially breached the subcontract as a
matter of law.
92
iii. Immaterial Breach
On the flip side of the coin, some litigants have argued that the court should determine
immateriality as a matter of law. The following breach, however, was not immaterial as a matter
of law:
In Pelco Construction Co. v. Chambers County, the First District Houston Court of
Appeals refused to find that an owner’s withholding of 10% of the contract price from a
contractor was an immaterial breach as a matter of law.
93
Chambers County withheld 10% of
two invoices submitted by Pelco for its work constructing a firehouse.
94
Chambers County
alleged that it withheld payment due to defects in the work and asserted three reasons as to why
the court should find that withholding 10% was an immaterial breach as a matter of law.
95
First,
Chambers County argued that 10% was a nominal amount to withhold.
96
Second, the withheld
amount was not intended to be permanent; once Pelco made corrections, the remaining amount
would be paid.
97
And third, Chambers County argued that Pelco’s failure to follow the payment
dispute resolution process prevented Pelco from claiming the breach as material.
98
The court
rejected all three arguments refusing to find immateriality as a matter of law because 1) case law
does not support the assertion that 10% contractual withholding is a nominal amount as a matter
of law; 2) the justification for withholding any amount was based on Pelco’s defective work
which was not established as a matter of law; and 3) it was unclear whether the contractual
provision at issue was applicable to the circumstances and even if it was, failure to follow the
86
Id. at *4.
87
Id. at *2.
88
Id. at *4.
89
Id.
90
Id.
91
Id.
92
Id. at *5.
93
Pelco Constr. Co. v. Chambers Cty., 495 S.W.3d 514, 524–26 (Tex. App.—Houston [1st Dist.] 2016, pet. denied).
94
Id. at 518.
95
Id. at 524–25.
96
Id. at 525.
97
Id.
98
Id. at 525–26.
10
6471760v2
dispute resolution procedures does not establish that Chambers County’s breach was
immaterial.
99
Further, the court reasoned that Chambers County did not provide Pelco with
notice and an opportunity to cure the defects as required under their contract, but simply issued
payment for less than the entire amount.
100
To find immateriality, the court would have to
conclude that Chambers County’s failure to notify Pelco of the alleged defects was immaterial,
but that Pelco’s failure to follow the claims procedure was material.
101
Nothing in Chambers
County’s motion for summary judgment established such conclusion as a matter of law.
102
The cases above demonstrate that even the same type of breach—i.e. failure to timely
perform, will in some instances be material as a matter of law and in other instances be a matter
for a jury to determine. Consequently, a prudent litigator should not count on any particular
breach being classified as material as a matter of law.
b. If a Contractor substantially performs, is the breach ever material?
Substantial performance of a construction contract throws another wrinkle into a material
breach analysis. In ordinary contract cases, a party who is in default cannot maintain a suit for
its breach.
103
This strict rule has been relaxed in the law of construction contracts by the doctrine
of substantial performance, which allows recovery to a building contractor who has breached but
substantially performed his contract.
104
This raises the question as to whether a contractor can
ever materially breach a contract that it substantially performs. It would appear the answer to
that question is no.
In a footnote, the Texas Supreme Court analogized the Bartush case to a construction
case in which the contractor achieves only substantial completion as follows: “[a] similar state of
affairs often arises in the context of construction contracts, when a contractor sues for the
balance due and owing on the contract and the property owner counterclaims for damages for
incomplete or defective performance.”
105
The Texas Supreme Court noted that “[i]n such cases
if the contractor has substantially completed performance, i.e. the contractor’s breach is not
material, then the contractor has a claim for the unpaid balance and the owner has a claim for
damages.”
106
“Substantial performance may be raised by a party seeking to recover on a contract that
was not fully performed or may be raised as the defensive issue of prior material breach by the
99
Id. at 526.
100
Id.
101
Id.
102
Id.
103
Gulf Pipe Line Co. v. Nearen, 138 S.W.2d 1065, 1068 (Tex. 1940).
104
Dobbins v. Redden, 785 S.W.2d 377, 378 (Tex. 1990); Vance v. My Apartment Steak House of San Antonio, Inc.,
677 S.W.2d 480, 481 (Tex. 1984); Atkinson v. Jackson Bros., 270 S.W. 848, 850 (Tex. Comm’n App. 1925, holding
approved).
105
Bartush-Schnitzius Foods Co. v. Cimco Refrigeration, Inc., 518 S.W.3d 432, 437 n.5 (Tex. 2017) (citing Vance,
677 S.W.2d at 480)). Accord, the Restatement (Second) of Contracts § 237, cmt. d (discussing the substantial
performance doctrine).
106
Id.
11
6471760v2
party defending a breach of contract action.”
107
However, the contractor has the burden to prove
substantial performance.
108
Consequently, the owner (or other upstream party) should consider
raising substantial performance as an issue if the contractor’s substantial performance is in
question.
109
In the end, a finding that the contractor substantially performed is similar to the material
breach analysis.
Indeed, “the doctrine of substantial performance overlaps with the requirement
that the breach of a contract must be material.”
110
“[T]he doctrine assumes, if there is substantial
performance, the breach is immaterial.”
111
For the contractor to meet its burden that it substantially performed a construction
contract,
the contractor must have in good faith intended to comply with the
contract, and shall have substantially done so in the sense that the
defects are not pervasive, do not constitute a deviation from the
general plan contemplated for the work, and are not so essential
that the object of the parties in making the contract and its purpose
cannot, without difficulty, be accomplished by remedying them.
112
Thus, the contractor must prove: (i) good faith; (ii) the absence of pervasive defects; and
(iii) that the defects can be remedied without the contract failing its essential purpose.
In the following case, the court found there was no material breach because the contractor
substantially performed. In Continental Dredging, the court found that an owner was not
excused from paying a contractor who substantially performed the contract.
113
The court equated
substantial performance with the lack of material breach. Specifically, the court found that the
contractor’s dredging operation did not achieve 36-feet required by the contract but almost
achieved that depth. The court noted that “[t]he ratio between what was left unperformed and
the total performance promised will frequently be decisive.”
114
The dredging contractor also
acted in good faith that it had concluded the contract.
115
As such, there was substantial
performance and no material breach.
116
107
St. Paul Mercury Ins. Co. v. Stewart Builders, Ltd., 01-09-00276-CV, 2011 WL 944377, at *6 (Tex. App.—
Houston [1st Dist.] Mar. 17, 2011, no pet.).
108
Vance, 677 S.W.2d at 482.
109
See Texas Pattern Jury Charge 101.46; cf Turner, Collie & Braden, Inc. v. Brookhollow, Inc., 642 S.W.2d 160,
165 (Tex. 1982) (discussing an implied finding of substantial performance due to the presentation of some evidence
that the contractor substantially performed); Movie Grill Concepts I, Ltd. v. CCM Grp., Inc., 05-02-00892-CV, 2003
WL 549425, at *2 (Tex. App.—Dallas Feb. 27, 2003, pet. denied) (discussing instruction in jury charge relating to
substantial performance).
110
See Gentry v. Squires Const., Inc., 188 S.W.3d 396, 403 n.3 (Tex. App.—Dallas 2006, no pet.).
111
Id.
112
Turner, Collie & Braden, Inc. v. Brookhollow, Inc., 642 S.W.2d 160, 164 (Tex. 1982).
113
Cont’l Dredging, Inc. v. De-Kaizered, Inc., 120 S.W.3d 380, 395–96 (Tex. App.—Texarkana 2003, pet. denied).
114
Id. at 395.
115
Id.
116
Id. at 396.
12
6471760v2
While not a construction dispute, the Fifth Circuit also held that a finding of substantial
performance establishes no material breach occurred and therefore does not excuse the other
party’s performance.
117
In Measday v. Kwik-Kopy Corp., the Fifth Circuit, applying Texas law,
analyzed the doctrine of substantial performance as applied to an employment/service
contract.
118
Measday was hired to serve as Kwik-Kopy’s regional franchise director under a 5-
year contract.
119
Before expiration of the contractual relationship between Measday and Kwik-
Kopy, Kwik-Kopy’s director of marketing told Measday he needed to sign a new agreement and
had no choice in the matter. Preferring to work under the existing contract, Measday refused to
sign the new contract and was subsequently terminated.
120
Measday sued for breach of contract.
The trial court found a valid 5-year contract and awarded Measday damages.
121
On appeal,
Kwik-Kopy argued that the jury instruction of substantial performance was in error.
122
Although
the Fifth Circuit agreed, the court held that such error did not require reversal because the facts
presented by Measday were sufficient to prove substantial performance.
123
Therefore, Kwik-
Kopy’s argument—that Measday did not substantially perform thereby excusing Measday’s
termination—must fail.
124
“A finding of substantial performance established there was no
material breach,” and therefore Kwik-Copy was not excused from performance.
125
These cases demonstrate that substantial performance may help certain parties to
demonstrate the lack of a material breach. In cases where the contractor or other downstream
party is less likely to prove substantial completion, it may be helpful to raise the issue due to the
burden shifting aspect of proving substantial performance.
c. Hypothetical Discussion of Bartush
Assume that the jury in the Bartush case found that Cimco breached first and the breach
was material (or that Bartush’s breach of contract was excused). Does Cimco’s breach excuse
Bartush from remitting any additional funds to Cimco? In addition to the amounts it withheld,
could Bartush seek an award of repair costs?
In the Bartush case, the Texas Supreme Court echoes the familiar rule that a material
breach by one party discharges the other from future performance.
126
But how far does that rule
extend? Under the hypothetical, would it justify the jury verdict in the Bartush case where the
trial court rendered judgement for Bartush for $168,079 and awarded nothing to Cimco?
Remember that Cimco was owed $113,400, which was the balance due on the contract.
117
Measday v. Kwik-Kopy Corp., 713 F.2d 118, 126 (5th Cir. 1983).
118
Id. at 124.
119
Id. at 121.
120
Id. at 122.
121
Id.
122
Id. at 123.
123
Id.
124
Id. at 125.
125
Id.
126
Bartush-Schnitzius Foods Co. v. Cimco Refrigeration, Inc., 518 S.W.3d 432, 437 (Tex. 2017).
13
6471760v2
The hypothetical is similar to the facts in Hooker v. Nguyen.
127
In that case, Hooker hired
Nguyen to build the interior of a salon.
128
Nguyen’s work was late and some defects existed in
the work.
129
At the end of the project, Hooker failed to pay $44,159.20 to Nguyen.
130
The jury
found that Nguyen failed to substantially perform but also awarded him the balance outstanding
on the work.
131
The jury also awarded Hooker $58,949.00 ($3,949.00 for costs of remedying or
repairing defects; $5,000.00 for liquidated damages for Nguyen’s late performance; and
$50,000.00 in diminution of value of the salon).
132
The Fourteenth District Houston Court of
Appeals determined that the jury finding that Nguyen failed to substantially perform was
equivalent to a finding of material breach excusing Hooker’s further performance.
133
Thus, the
appellate court reversed and rendered.
134
Nguyen was awarded nothing and Hooker was
awarded the damages found by the jury.
135
Based upon the precedent in Hooker, Cimco would not be entitled to its balance due and
Bartush would be entitled to its cost of repair. This result raises questions relating to an owner
receiving a windfall due to not paying for defective work and being awarded the cost of repair.
Perhaps, however, this result was brought about due to the lack of a claim for quantum meruit.
136
IV. Other common breach scenarios – Continuing Performance
The first to breach rule stated in Mustang Pipeline—that “when one party to a contract
commits a material breach of that contract, the other party is discharged or excused from future
performance”—applies only so long as the parties do not treat the contract as continuing in
effect.
137
Chilton Ins. Co. v. Pate & Pate Enterprises, Inc. illustrates an example of when the non-
breaching party elects to continue the contract after a breach by its contractual counter-party, but
then later attempts to withhold payments based on these prior material breaches. In Chilton,
Chilton provided a performance bond on behalf of Caliber, the subcontractor hired by the general
contractor, Pate, to perform a public works project.
138
After Caliber defaulted, Chilton entered
into a takeover agreement with Pate, whereby Chilton agreed to complete Caliber’s work and
Pate agreed to pay Chilton in accordance with the terms of Caliber’s subcontract.
139
Due to
delays and problems with Chilton’s work, Pate withheld payment from Chilton, even though
127
14-04-00238-CV, 2005 WL 2675018 (Tex. App.—Houston [14th Dist.] Oct. 20, 2005, pet. denied).
128
Id. at *1.
129
Id.
130
Id. at *3.
131
Id. at *3.
132
Id. at *3 n.2.
133
Id. at *10.
134
Id. at *11.
135
Id.
136
See Beeman v. Worrell, 612 S.W.2d 953, 956 (Tex. Civ. App.—Dallas 1981, no writ) (holding that recovery in
quantum meruit was proper where contractor failed to substantially perform and where owner had payments
outstanding).
137
Gupta v. E. Idaho Tumor Inst., Inc., 140 S.W.3d 747, 756 (Tex. App.—Houston [14th Dist.] 2004, pet. denied).
138
Chilton Ins. Co. v. Pate & Pate Entes., Inc., 930 S.W.2d 877, 888 (Tex. App.—Corpus Christi 1996, writ
denied).
139
Id.
14
6471760v2
Chilton continued to perform the work.
140
When the project was complete, Pate acknowledged
that Chilton was owed a balance under the takeover agreement, but claimed that it had been
damaged by Chilton’s poor performance and delays and demanded reimbursement from
Chilton.
141
Chilton filed suit alleging, among other claims, breach of contract.
142
Pate
counterclaimed to recover its damages for Chilton’s breach of contract.
143
In its live pleadings,
Pate judicially acknowledged that Chilton was entitled to a credit against the actual damages it
allegedly owed to Pate.
144
Pate, however, argued that its failure to pay Chilton the remaining amount owed under
the takeover agreement was excused by Chilton’s prior material breach.
145
The court
acknowledged the general rule that “[w]here one party materially breaches a contract, the non-
breaching party is forced to elect between two courses of action—continuing performance or
ceasing performance. Treating a contract as continuing, after a breach, deprives the non-
breaching party of any excuse for terminating their own performance.”
146
The court found
that Pate treated the contract with Chilton as continuing because “by its own words, [Pate]
admits it ‘did not seek to declare the contract terminated [upon the breach], but rather operated
within the terms of the contract and performed its obligations under such contract.’”
147
The court
rejected Pate’s argument that the election of remedies doctrine applied to Chilton when Pate first
withheld a progress payment because Pate was permitted to withhold this payment under the
subcontract, finding that “[a]n election does not arise until the other party materially breaches the
contract. Pate’s failure to comply with the subcontract did not occur at the time it withheld
progress payments. If a breach occurred, it was when Pate withheld final payment after the
Project was accepted by the City.”
148
Instead, the election of remedies occurred when Pate
determined that Chilton materially breached the contract—at that time, Pate could have either
discontinued its own performance, rescinded the contract and sued for material breach, or
continue its performance and lose Chilton’s material breach as an excuse for its own non-
performance.
149
By its own actions, Pate elected to treat the contract as continuing, and therefore
forfeited any excuse for its own breach of failing to pay the admitted credit to Chilton.
150
Similarly, in Eco Built, the court found that a contractor, Landmark, could not refuse to
pay a terminated subcontractor, Eco Built, for work completed before the termination even
though the jury found that Eco Built breached the contract first and the breach was material.
151
Specifically, the court held that Landmark waived Eco Built’s prior breach as an excuse for
terminating its own non-performance (i.e. not paying Eco Built’s invoices before termination).
152
140
Id.
141
Id.
142
Id.
143
Id.
144
Id. at 885–86.
145
Id. at 887.
146
Id. at 887–88 (citations omitted) (emphasis added).
147
Id. at 888.
148
Id.
149
Id.
150
Id.
151
Eco Built, Inc. v. Lulfs, 2010 WL 3629821, at *6 (Tex. App.—Austin, Sep. 17, 2010).
152
Id. at *5.
15
6471760v2
As a result, the payments owed to Eco Built were offset against the damages incurred by
Landmark.
153
While parties are required to continue to perform after another party breaches the contract
if they elect to treat the contract as continuing, that does not mean a claim for damages is
waived.
154
The non-breaching party’s election of remedies “affects only whether the non-
breaching party is required to perform fully after the breach.”
155
“[A]ny action indicating an
intent to continue [the contract] will operate as a conclusive choice,” and while the non-
breaching party will be deprived of “any excuse for ceasing performance on his own part,” the
injured party will not be deprived of “his cause of action for the breach which has already taken
place.”
156
A party’s “continuing performance after another party’s breach is not a waiver of the
right to recover damages due to the breach, and a non-breaching party’s honest efforts to induce
the party in default to perform the contract do not constitute waiver.” As such, a prior material
breach is treated more like an immaterial breach when the non-breach party continues to
perform.
V. Jury charge
Drafting the jury charge is complicated by dueling breach claims. The biggest mistake is
assuming that one size fits all. While you can begin with the jury charges recommended by the
Texas PJC and the Texas Supreme Court, all charges have to be adjusted to the needs of the case.
Texas Pattern Jury Charge 101.2 (2016) includes the following comment with respect to
competing claims of material breach:
Disjunctive question for competing claims of material breach. If both
parties allege a breach of contract against one another, the court can ask
the breach-of-contract question disjunctively, together with an appropriate
instruction directing the jury to decide who committed the first material
breach.
157
An alternative way to submit competing claims of breach of an
agreement is set forth below.
QUESTION 1
Did Don Davis fail to comply with the agreement?
153
This case illustrates the ease with which parties can be considered to have continued performance after the
breach. The contract was executed on September 27, 2002. On November 15, 2002 Landmark served notice of
default and on December 6, 2002, Landmark terminated the contract. While Landmark made a partial payment after
disputes arose and amended the contracts at issue, this continued “performance” only lasted for a couple of weeks.
There was no jury question regarding continued performance. Had Landmark not paid anything to Eco Built the
results may have been different in the case.
154
Chilton Ins. Co. v. Pate & Pate Enters., Inc., 930 S.W.2d 877, 888 (Tex. App.—Corpus Christi 1996, writ
denied) (citing Western Irr. Co. v. Reeves Land Co., 233 S.W.2d 599, 602–03 (Tex. App.El Paso 1950, no writ)).
155
Avasthi & Assocs., Inc. v. Dronamraju, No. 01-11-00786-CV, 2012 WL 6644873, at *8 (Tex. App.Houston
[1st Dist.] 2012, pet. denied) (mem. op.).
156
Avasthi, 2012 WL 6644873, at *7 (quoting Compass Bank v. MFP Fin. Servs., Inc., 152 S.W.3d 844, 858 (Tex.
App.Dallas 2005, pet. denied)).
157
Mustang Pipeline Co. v. Driver Pipeline Co., 134 S.W.3d 195, 200 (Tex. 2004).
16
6471760v2
[Insert instructions, if appropriate.]
Answer “Yes” or “No.”
Answer: ____________
QUESTION 2
Did Paul Payne fail to comply with the agreement?
[Insert instructions, if appropriate.]
Answer “Yes” or “No.”
Answer: ____________
If you answered “Yes” to Question 1 and Question 2, then answer
Question 3. Otherwise, do not answer Question 3. QUESTION 1
QUESTION 3
Who failed to comply with the agreement first?
Answer “Don Davis” or “Paul Payne.”
Answer: ____________
The pattern jury questions in Pattern Jury Charge 101.2 are a derivation of the charge
recommended by the Texas Supreme Court in Mustang Pipeline. In that case, the court noted
that the parties could have avoided having the jury finding both parties in breach “had the trial
court submitted the breach of contract question disjunctively (“Did Driver Pipeline Company or
Mustang Pipeline Company fail to comply with the parties’ contract?”) accompanied by an
appropriate instruction directing the jury to decide who committed the first material breach.”
158
However, the Committee on Pattern Jury Charges elected to re-state the disjunctive question as
two questions and pose a third question relating to order of breach which, according to the
Committee, focuses on the “defense of prior material breach.”
159
Additionally, the Committee
recommends predicating damages only on an affirmative finding of Question 1 and 2 but not 3
relating to who failed to comply first.
The Committee on Pattern Jury Charges of the Texas State Bar also provides the
following commentary with respect to materiality listing the factors for determining materiality
and noting:
158
Id.
159
PJC 101.2 Comments to disjunctive question for competing claims of material breach (noting Question 3 submits
the defense of prior material breach).
17
6471760v2
Material breach. If the parties dispute whether the alleged breach is a
material one, the court should insert any or all of the following instructions
regarding materiality, as appropriate:
A failure to comply must be material.
Interestingly, the PJC arguably does not contemplate a nonmaterial breach like the one discussed
in Bartush (which the court found justified an award of damages but required continued
performance
160
) because it states that a failure to comply must be material or alternatively
permits the parties to assume the breach was material.
In the Bartush case, the parties appear to have followed the instruction of PJC 101.21-22
which recommends the following question when a party submits one or more defenses to a
contract suit:
PJC 101.21 Defenses—Basic Question
If you answered “Yes” to Question [101.1], then answer the
following question. Otherwise, do not answer the following question.
QUESTION ______
Was Don Davis’s failure to comply excused?
PJC 101.22 Defenses—Instruction on Plaintiff’s Material Breach
(Failure of Consideration)
Failure to comply by Don Davis is excused by Paul Payne’s
previous failure to comply with a material obligation of the same
agreement.
Answer “Yes” or “No.”
Answer:__________
Thus, prior material breach was submitted as a defense instead of part of Question 2 which asked
whether Cimco failed to comply with the contract. Interestingly, had materiality been raised in
connection with Question 2 relating to Cimco’s failure to comply it is possible the jury would
have found Cimco did not breach because the jury later found that Cimco did not fail to comply
with a material obligation of the agreement in Question 4. If the jury had found that Cimco did
not breach but Bartush did, Bartush would not have been awarded any damages.
160
Bartush-Schnitzius Foods Co. v. Cimco Refrigeration, Inc., 518 S.W.3d 432, 437 (Tex. 2017).
18
6471760v2
In CFS Forming Structures Co. v. Flintco, Inc., the Fifth Circuit approved another form
of jury instructions in connection with competing breach scenarios.
161
In this case, Flintco
contracted with CFS to perform the concrete scope in connection with a conference center and a
hotel. While several schedules were issued, Flintco became concerned that CFS was not timely
performing the concrete work.
162
Before the project manager went on vacation, he sent a cure
notice to CFS requesting CFS commence curing its delay in beginning the concrete work. While
he was out, CFS began the slab work by laying down vapor barriers, applying pest control,
grading the site, and similar actions consistent with preparing the concrete work.
163
The project
manager returned and terminated CFS because it had failed to undertake “significant carton
form” work.
164
The submitted jury questions were as follows:
165
Question 1: Do you find that CFS was in compliance with the
master project schedule on September 28? If “No” proceed to
question 2; if yes, proceed to question 3.
Question 2: Do you find that CFS satisfied the notice in the “cure
letter” of September 28 by commencing operations? If yes,
proceed to question 3; if “no” proceed to question 4.
Question 3: What amount of money would compensate CFS for
Flintco’s termination?
Question 4: What amount of money would compensate Flintco for
CFS’s breach?
The jury found that CFS was not in breach of the subcontract on September 28 and awarded
damages for Flintco’s unjustified termination.
166
Flintco argued that the district court erred by
refusing to submit the questions in the disjunctive as recommend by Mustang Pipeline. In
rejecting Flintco’s argument, the Fifth Circuit opined that the purpose behind the Mustang
Pipeline court’s instruction was to capture the concept of materiality. Specifically, the Fifth
Circuit held that “[t]he district court’s jury instruction here adequately capture the question of
materiality despite their not being worded in the disjunctive [because] [t]he charge contains the
implicit assumption that the breaches, if they occurred were material.
167
That is, the jury questions require that, (1) if the jury finds that
CFS breached the subcontract by failing to comply with the CPM,
Flintco must be awarded damages, but (2) if CFS was in
compliance, then Flintco’s termination was wrongful and the jury
must determine the quantity of damages incurred by CFS. Even
though they do not explicitly require the jury to decide materiality,
161
CFS Forming Structures Co., Inc. v. Flintco, Inc., 393 F. App’x. 136, 142 (5th Cir. 2010).
162
Id. at 139.
163
Id.
164
Id.
165
Id. at 139–40.
166
Id. at 140.
167
Id. at 142.
19
6471760v2
these instructions will nevertheless establish which breach, if any,
is material. And, because of the “cure” provision, CFS could only
be in breach under the instant facts if it were first notified of a
putative breach and afforded an opportunity to cure. There is no
question that Flintco terminated the subcontract and that it
purported to do so because of CFS’s putative failure to cure the
delay outlined in the “cure letter.” It necessarily follows that if
CFS was not actually in breach vel non, then the termination for
that breach was wrongful.
168
Because the jury charge addressed materiality and prevented conflicting findings, it was
proper.
169
Upon review of the cases above, there is much more guidance with respect to submitting
questions regarding breaches that are clearly material. The Texas Pattern Jury Charge fails to
provide guidance with respect to common breach scenarios where one of the breaches was
immaterial or where the parties continue to perform after the original breach. Likewise, Mustang
Pipeline and Flintco do not address a scenario like that in Bartush where the court found that
Cimco breached first but its breach was not material.
While the Bartush Court used implied findings to resolve the issues before it, the Texas
Supreme Court made no further recommendations for handling jury questions relating to material
breach in that case. As such, practitioners are left without much guidance to draft jury charges
where one breach was not material or the first breach was material but later performance was not
excused because the non-breaching party continued to perform. While there are multiple ways to
ask the jury to decide completing breach claims, to the extent the parties believe that one of the
breaches was immaterial, consider a modification of the questions posed by Bartush and Cimco
as follows: Question 1 and 2 regarding each parties’ failure to comply with the agreement at
issue, Question 3 regarding order of breach (predicated on an affirmative finding for 1 and 2) and
then express questions regarding materiality with appropriate predicates. The materiality
questions are suggested in lieu of asking the jury to determine whether a party’s breach was
excused to avoid having a court decide whether a finding of materiality or immateriality was
implied. If additional questions are used regarding materiality as suggested, the jury will decide
materiality and it will not be implied either through asking who breached first or in a question
relating to whether a parties’ breach was excused.
VI. How are attorneys’ fees affected by competing breach claims?
Dueling breach claims also create unique issues with respect to attorneys’ fees. In
Bartush, the jury was asked about both parties’ fees and awarded Bartush fees but not Cimco.
170
According to Cimco, it was not awarded fees due to conditional submission of the question
regarding its fees.
171
168
Id. at 142–43.
169
Id. at 143.
170
Bartush-Schnitzius Foods Co. v. Cimco Refrigeration, Inc., 518 S.W.3d 432, 435 (Tex. 2017).
171
Id. at 438.
20
6471760v2
In connection with competing breach claims, both parties may be awarded fees under
certain circumstances. The analysis is varied depending upon the existence of a prevailing party
clause.
a. No prevailing party clause
Texas Civil Practice and Remedies Code § 38.001 is the statute that Texas litigants look
to for recovery of attorneys’ fees in connection with breach of contract claims. Parties are
entitled to recover fees from individuals and corporations under Texas Civil Practice and
Remedies Code § 38.001 even in the absence of a prevailing party when they (1) prevail on a
cause of action for which attorneys’ fees are recoverable, and (2) recover damages.
172
Under the predecessor to Texas Civil Practice and Remedies Code § 38.001, the Texas
Supreme Court analyzed the ability of both parties to recover fees in the absence of a prevailing
party clause. In McKinley v. Drozd, a general contractor brought suit against homeowners to
recover the balance due on a construction contract and its attorneys’ fees.
173
The homeowners
asserted a competing claim for breach of contract and requested attorneys’ fees.
174
The trial
court awarded both parties damages under their breach claims as well as equal attorneys’ fees.
175
The Texas Supreme Court addressed the issue of whether a party needs a net recovery in order to
recover attorneys’ fees under Texas Civil Statutes, article 2226—the predecessor to Texas Civil
Practice and Remedies Code § 38.001.
176
The court looked to the wording of the statute and
concluded, “all that is required to obtain attorneys’ fees is a ‘just amount owing’ not tendered
within 30 days.”
177
Therefore, in competing breach claims, even if a party’s damages are
completely offset, the party may still recover its attorneys’ fees.
178
The party who prosecutes a breach of contract claim but recovers no damages, cannot be
awarded fees under § 38.001 because he did not receive relief on a valid claim.
179
Specifically,
§ 38.001(8) provides that a party “may recover reasonable attorneys’ fees from an individual or
corporation, in addition to the amount of a valid claim and costs, if the claim is for . . . an oral or
written contract.”
180
In Green v. Solis, although a jury found that Solis failed to comply with a
subcontract, the jury awarded zero damages to Green for Solis’ breach.
181
Because Green failed
to recover damages on its breach of contract claim, Green was not entitled to recover attorneys’
fees under § 38.001.
182
172
Green Int’l, Inc. v. Solis, 951 S.W.2d 384, 390 (Tex. 1997) (citing State Farm Life Ins. Co. v. Beaston, 907
S.W.2d 430, 437 (Tex. 1995)).
173
McKinley v. Drozd, 685 S.W.2d 7, 8 (Tex. 1985).
174
Id.
175
Id.
176
Id. at 10.
177
Id.
178
Id. at 11.
179
Green Int’l, Inc. v. Solis, 951 S.W.2d 384, 389–90 (Tex. 1997).
180
TEX. CIV. PRAC. & REM. CODE § 38.001(8).
181
Green, 951 S.W.2d at 386.
182
Id. at 390.
21
6471760v2
b. Prevailing party clause
In Intercontinental Group Partnership v. KB Home Lone Star, L.P., the Texas Supreme
Court, identified the standard for determining the prevailing party in a breach of contract action
in connection with a prevailing party clause. In considering whether an award of contractual
attorneys’ fees was proper, the court determined that a party “prevails” on a claim “when actual
relief on the merits of his claim materially alters the legal relationship between the parties by
modifying the defendant’s behavior in a way that directly benefits the plaintiff.”
183
Thus, the concept of “prevailing party” as a claimant includes not just successfully
proving or defending against a claim but also receiving relief. In a breach of contract action
where a party seeks § 38.001 attorneys’ fees,
184
the party who “prevails” must be the breach of
contract claimant who “prove[s] compensable injury and secure[s] an enforceable judgment in
the form of damages or equitable relief.”
185
On the other hand, in connection with a prevailing party clause, a party may—in many
instances—be awarded fees for successfully defending a breach of contract claim.
186
Thus, the
analysis of cost of defense is different for competing breach claims where a prevailing party
clause exists and where one does not because there is no award of fees under § 38.001 for a
successful defense.
In www.Urban.inc. v. Drummond, the court discussed order of breach in connection with
whether a defendant could be a prevailing party entitled to attorneys’ fees in connection with its
defense of a breach of contract claim.
187
In the Drummond case, Chris Drummond signed a
Residential Buyer/Tenant Representation Agreement in 2011 in which Drummond agreed to
exclusively work through Urban for six months. Under the terms of the agreement, Urban was
entitled to a commission based on the gross sales price of the property. The agreement also
provided for a payment to Urban upon Drummond’s default. The agreement also contained the
following attorneys’ fees provision:
ATTORNEY’S FEES: If Client or Broker is a prevailing party in
any legal proceeding brought as a result of a dispute under this
agreement or any transaction related to this agreement, such party
183
Intercontinental Grp. P’ship v. KB Home Lone Star L.P., 295 S.W.3d 650, 654 (2009) (quoting Farrar v. Hobby,
506 U.S. 103, 111–12 (1992)). Note that the Court left open the issue of whether a defendant who successfully
defends a breach of contract claim would be entitled to contractual attorneys’ fees.
184
TEX. CIV. PRAC. & REM. CODE § 38.001.
185
KB Home, 295 S.W.3d at 652 (defining “prevail” in relation to breach of contract claimant in contractual
attorneys’ fees case); Green, 951 S.W.2d at 390 (defining “prevail” in relation to breach of contract claimant under
T
EX. CIV. PRAC. & REM. CODE § 38.001 breach of contract case); Mustang Pipeline Co. v. Driver Pipeline Co., 134
S.W.3d 195, 201 (Tex. 2004) (holding party not entitled to attorneys’ fees where party has valid breach of contract
claim but awarded no damages).
186
Chevron Phillips Chem. Co. LP v. Kingwood Crossroads, L.P., 346 S.W.3d 37, 70 (Tex. App.—Houston [14th
Dist.] 2011, pet. denied) (holding fees for defense of claim were proper where “contractual provision entitling a
‘prevailing party’ to recover attorneys’ fees does not distinguish between successful prosecution and successful
defense of a claim”); see also VSDH Vaquero Venture, Ltd. v. Gross, 05-16-01041-CV, 2017 WL 3405312, at *5
(Tex. App.—Dallas Aug. 9, 2017, no pet.).
187
WWW.URBAN.INC. v. Drummond, 508 S.W.3d 657, 663 (Tex. App.—Houston [1st Dist.] 2016, no pet.), reh’g
denied in part (Feb. 7, 2017).
22
6471760v2
will be entitled to recover from the non-prevailing party all costs of
such proceeding and reasonable attorney’s fees.
Only Urban’s breach of contract claim and Drummond’s affirmative defense of prior material
breach and breach of fiduciary duty were submitted to the jury. The jury found that Urban
materially breached first through its failure to use best efforts under the agreement. The jury also
found the Drummond breached. Neither party was awarded damages. Urban contended that the
trial court erred by awarding attorneys’ fees to Drummond because Drummond is not a
“prevailing party” under the agreement.
188
Urban asserted several arguments to attempt to show that it was the prevailing party
including that Drummond’s breach necessitates a finding that Drummond was not the prevailing
party.
189
Specifically, Urban argued that Drummond could not recover attorneys’ fees based on
his defense of Urban’s breach of contract claim because the jury found that Drummond breached
the agreement and there is no jury finding that Drummond’s breach was excused. The court
reasoned, however, that the jury’s findings demonstrate that Drummond’s failure to comply with
the agreement was excused as a matter of law by Urban’s prior material breach. As such, the
order of breach can also affect the party designated as the prevailing party.
The determination of the prevailing party under a prevailing party clause is even more
complicated by facts similar to those in McKinley and in Bartush where both parties prevail on a
claim and are awarded damages particularly due to the lack of case law available to provide
guidance on the issue. While it was at least partially rejected in KB Home,
190
some courts
continue to rely upon the “main issue” analysis in other contexts.
191
Thus, some courts may
determine the identity of a prevailing party through an analysis of who prevailed on the main
issue. The author also has experience with arbitrators permitting both parties to recover fees
without engaging in an analysis of who prevailed on the main issue. If parties desire more
188
Id. at 665.
189
Id. at 670.
190
KB Home, 295 S.W.3d at 661–62 (rejecting the dissenting opinion’s “main issue” analysis used to define a
“prevailing party”).
191
Drummond, 508 S.W.3d at 667–68 (“Therefore, we do not read KB Home as rejecting “main issue” analysis in
all cases in which a contractual attorneys’ fee provision controls, but, rather, only in those cases in which such
analysis is incompatible with a controlling contractual provision.”). See Silver Lion, Inc. v. Dolphin Street, Inc., 01-
07-00370-CV, 2010 WL 2025749, at *18 (Tex. App.—Houston [1st Dist.] May 20, 2010, pet. denied) (relying upon
pre-KB Home authorities and holding defendant who prevailed on “main issue” was entitled to attorneys’ fees
pursuant to contract provision); see also SEECO, Inc. v. K.T. Rock, LLC, 416 S.W.3d 664, 674 (Tex. App.—
Houston [14th Dist.] 2013, pet. denied) (holding defendant who prevailed on “main issue” was entitled to attorneys’
fees pursuant to contract provision); Bhatia v. Woodlands N. Houston Heart Ctr., PLLC, 396 S.W.3d 658, 670–71
(Tex. App.—Houston [14th Dist.] 2013, pet. denied) (same); Johnson v. Smith, No. 07-10-00017-CV, 2012 WL
140654, at *2 (Tex. App.—Amarillo Jan. 18, 2012, no pet.) (same). In a case tried to a jury, the issues that are fully
litigated and properly submitted to the jury provide compelling evidence of the main issues in that case. See Bhatia,
396 S.W.3d at 670–71 (holding that, in suit involving multiple claims and counterclaims based on breach of
contract, tort, and statutory causes of action, some of which “were essentially abandoned, and others were defeated
in motions practice and were not submitted to the jury or raised in th[e] appeal,” main issues were those that were
fully litigated, properly submitted to jury, and formed the basis of the “vast majority of the [trial] testimony”); see
generally Johnson, 2012 WL 140654, at *3 (stating that parties who “obtained favorable findings on all major jury
issues” and take-nothing judgment in their favor were prevailing parties under contract).
23
6471760v2
certainty with respect to fees and the identity of a prevail party, the best practice would be to
define the prevailing party in the attorneys’ fee provision.
VII. Conclusion
In analyzing competing breach claims, attorneys should consider materiality first and
then analyze whether parties continued to perform. Construction litigators should also be
mindful that not all breaches are material and that damages may also be awarded for certain non-
material breaches. In drafting the jury charge, consider both material and immaterial breaches
and remember that the Texas Pattern Jury Charge does not address immaterial breaches or
continuing performance after a material breach. In determining strategy in settlement and trial,
attorneys should also consider the effect of competing breach claims as well as the existence of a
prevailing party clause on attorneys’ fees.
1
One Breach, Two Breach,
Old Breach, New Breach:
An Analysis of Competing Contract Claims in
Light of Bartush-Schnitzius Foods v.
Cimco Refrigeration
Construction Law Foundation of Texas, 31
st
Annual Construction Law Conference
Presented by: Amy K. Wolfshohl
Competing Breach Claims
When both parties assert claims for breach of
contract questions arise regarding:
Who breached first
Whether the breaches were material
Whether performance continued after a breach
Whether either party or both are entitled to fees
Analysis of these issues should begin with
established case law
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
2
First Breach is Material
First breach is material [Mustang Pipeline]
Non-breaching party is no longer required to
perform
Second breach by non-breaching party is excused
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
Material Breach + Continued
Performance
First breach is material but non-breaching party
continues to perform [Chilton]
Non-breaching partys performance is not excused
Second breach by non-breaching party is not
excused
Claim for damages for first breach is not waived
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
3
First Immaterial Breach
What is the effect of the first breach being
immaterial?
Are damages available for the immaterial breach?
Does the first material breach following the
immaterial one negate the immaterial breach?
The questions were answered recently and
definitely by the Texas Supreme Court.
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
Bartush-Schnitzius Foods v. Cimco
Refrigeration
Bartush hired Cimco to build refrigerated
storage for seafood dips.
The refrigerated storage could not maintain
the temperature necessary for the dip without
ice forming on the fan motors.
When Bartush discovered the problem, it had
already paid Cimco $306,758, but still owed
$113,400.
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
4
Bartush-Schnitzius Foods v. Cimco
Refrigeration
The parties did not agree on how to proceed,
and the manufacturer hired an engineer.
The engineer recommended a warm-glycol
defrost unit, and Bartush hired another
contractor to install the unit at a cost of
$168,079.
After the warm-glycol defrost unit was
installed, the system was able to maintain a
temperature of 35 degrees.
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
Competing Breach Claims
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
Cost of Defrost Unit
Bartush
Cimco
5
Jury Findings
1. Both parties breached the contract
2. Cimco breached first
3. Bartush’s breach was not excused
4. Bartush was entitled to $168,079 (the cost of
installing the warm-glycol defrost unit)
5. The contractor was entitled to $113,400 (the
contract balance)
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
Trial Court
Although the jury found both parties breached
the contract and that Bartush’s breach was
not excused, the trial court believed it favored
Bartush and rendered judgment in favor of
Bartush for $168,079.
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
6
Fort Worth Court of Appeals
Reversal
Bartush breached the contract, and the jurys
failure to find the breach was not excused
necessarily implied a finding that Cimco’s first
breach was nonmaterial.
Bartush’s failure to pay was a material breach
as a matter of law, rendering irrelevant the
jurys finding that Cimco breached first and
precluding Bartush’s recovery.
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
Fort Worth Court of Appeals
Reversal
Breach 1 – Cimco’s failure to perform (immaterial)
Breach 2 – Bartush’s non-payment (material as a MOL)
Cimco wins and Bartush gets nothing
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
7
Texas Supreme Court
“It is a fundamental principle of contract law
that when one party to a contract commits a
material breach of that contract, the other
party is discharged or excused from further
performance.”
By contrast, when a party commits a
nonmaterial breach, the other party is not
excused from future performance but may
sue for the damages caused by the breach.
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
Texas Supreme Court
Materiality was appropriately determined by
the jury unlike in Mustang Pipeline where
materiality was determined as a matter of law
Materiality was determined by the jury in
connection with finding that Bartush’s breach
was not excused (not in the initial questions
regarding who breached and which breach
was first)
Resulted in implied finding that Cimco’s breach
was immaterial
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
8
Immaterial Breach is Relevant
“While a partys nonmaterial breach does not
excuse further performance by the other
party, neither does the second breach excuse
the first.
“[A] material breach excuses future
performance, not past performance.
Court seems to imply that Bartush’s non-
payment was material even though it was not
discussed by the court or decided by the jury.
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
Immaterial Breach is Relevant
Cimco breached first but its breach was
immaterial
Bartush breached second
Bartush was required to continue to perform
(pay the balance due) but was also entitled to
damages for Cimco’s immaterial breach
Result: Bartush’s damages offset by amounts
owed to Cimco (assuming the appellate court
determines issues in a manner that favors
Bartush on remand)
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
9
Closer Look at the Jury Charge
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
Jury Question/Answer Potential for
Conflict
Conflicting Result Resolution by TXSC
Q1 and Q2 – Whether
the parties complied
with agreement?
Neither complied.
Q3 – Who breached
first? Cimco
[No instruction on
materiality]
PJC – Implies
materiality in the
absence of an
instruction or
question.
Trial court concluded
that verdict favored
Bartush.
Appellate court
disregarded finding
and concluded
Bartush’s breach was
material as a MOL.
Cimco’s first breach
entitled Bartush to
damages.
Q4 – Was Bartush’s
failure to comply
excused due to Cimco’s
prior material breach?
No.
Materiality factors as
an affirmative
defense potentially
conflict with the PJC
assumption of
materiality.
Disregarded by trial
court.
Implied a finding that
Cimco’s breach was
immaterial which
meant Bartush was
required to perform.
Jury Questions to Consider
Q1 and Q2 – Failure to comply (same)
Q3 – Who breached first? (same)
Q4 and 5 – Explicitly ask about materiality of
breach to the extent a jury answers “yes” to
questions 1 and 2
No implied findings
Enables the jury to determine both material and
immaterial breach
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
10
Materiality as a Matter of Law
While materiality is typically determined by
the fact finder, some breaches are material as
a matter of law.
When a breach can be determined as a matter
of law, you can recommend a client cease its
performance without worrying about whether
a fact finder will also determine that the client
breached.
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
Material Breaches as a
Matter of Law
Failure of a contractor to prove substantial
performance [Hooker v. Nguyen] relieved
owner of remaining payment obligations
Contractor breached as a matter of law
because: (i) the contract contained a hard
deadline, a time is of the essence clause, and
contemplated avoidance of delays and (ii) an
objective inability to cure existed [Mustang
Pipeline]
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
11
Consider a Hypothetical
Assume that the jury in Bartush found that
Cimco breached first and that Bartush’s
breach was excused (i.e. Cimco’s breach was
material). Was Bartush permitted to keep the
contract balance owed to Cimco and receive
an award of repair costs?
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
Hypothetical
Likely yes. See Hooker v. Nguyen
Windfall for the owner who was awarded
repair costs and entitled to withhold the
contract balance
Consider a quantum meruit claim when
representing a contractor under similar
circumstances
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
12
Attorneys’ Fees
Competing breach claims complicate the
analysis of fee awards
Analysis depends upon whether there is a
prevailing party clause in the contract
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
Recovery of Attorneys’ Fees under
Tex. Civ. Prac. Rem. Code §38.001
Recovery for claimant from individuals and
corporations when:
Claimant prevails on a breach of contract action;
and
Recovers damages.
Zero damages = Zero fees [Green v. Solis]
Attorneys’ fees may be awarded even if the
damages award by one party is completely
offset by the other award [McKinley v. Drozd]
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
13
Recovery of Attorneys’ Fees with a
Prevailing Party Clause
To be a prevailing party, a claimant who seeks
money damages on a breach claim must
prevail on the claim and be awarded damages
[Intercontinental Group Partnership v. KB
Home Lone Star, L.P.]
A defendant must prevail, but does not need
to be awarded damages.
Party seeking an award of fees does not need
to be concerned with the type of entity sued.
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
Poll
Can both parties recover fees when:
Both parties assert breach claims
Both parties are awarded damages
The contract includes a prevailing party clause
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
14
Main Issue?
Main issue analysis rejected in part by the
Texas Supreme Court in KB Home.
Some courts continue to apply it
Would seem to make sense that there is one
prevailing party in a dispute BUT…
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
Two Prevailing Parties?
No case specifically addresses the issue
Parties can alternatively request fees against
individuals and corporations under §38.001
[Alta Mesa Holdings, LP v. Ives, 488 S.W.3d
438, 455 (Tex. App.—Houston [14th Dist.]
2016, pet. denied)].
Consider defining the prevailing party in your
contract to ensure certainty of any result you
want to achieve.
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
15
Final Thoughts
Don’t neglect the immaterial breach claim
Remember that the PJC does not address
claims for non-material breach
Materiality will typically be determined by a
fact finder and not as a matter of law
Use a prevailing party clause with a definition
of the prevailing party to get more certainty in
attorneys’ fee awards
Construction Law Foundation of Texas,
31st Annual Construction Law Conference
Any Questions?
Thanks to Dr. Seuss for inspiring the title of
this presentation.
Construction Law Foundation of Texas,
31st Annual Construction Law Conference